Friday, June 26, 2015
June 26 -- One More Stone Project....
The cinder block retaining wall where we planted Grandmom Speer's raspberries got the stone treatment this week. Turns out we have a lot of extra stone laying around.....
Tuesday, June 23, 2015
June 22 -- Smoke House Stone Finish Line
The masons are closing in on the last section of stone to be installed.
Friday, June 19, 2015
June 19 -- Ava's Bathroom Paint Treatment
Ava has taken an active role in completing the paint feature in her bathroom: a silhouette of the key structures of the New York City skyline.
Wednesday, June 17, 2015
June 17 -- Bar Cabinet Doors, Shelves, and Details
Cabinet doors, shelves, and insulated column around the plumbing went in today.
A photo of the detailed scribing done to fit the panels to the stone wall:
Tuesday, June 16, 2015
June 16 -- The Bar Comes Together!
The shelves still need to be installed, and the plumbing hidden, but bit by bit the bar back is nearing completion.
Friday, June 12, 2015
June 12 -- "Let There Be Light," Part Three
We have cut a hole to install another window into the garage attic, which will
allow much more light and ventilation.
Thursday, June 11, 2015
Wednesday, June 10, 2015
June 10 -- Steady Progress Today
We are using stone from the demolished interior wall, as well as stone we can scrounge up around the property.
That long stone between the two windows was once a lintel over one of the 18th century windows.
Tuesday, June 9, 2015
June 9 -- Trim for the Other Garage Bays
Here again, we have used the milled elm from onsite trees to provide trim for "my" garage bays.
No parking allowed, yet:
Friday, June 5, 2015